Project management ch 9 – 6th edition reducing project duration

Reducing Project Duration
Project Management Ch 9
6th Edition

Your Results:
The  answer for each question is indicated by a  .

 

1    
Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year. This may lead to a project that must be done faster than anticipated. This is an example of reducing project duration caused by:
    A)
Imposed project deadlines
    B)
Time to market
    C)
Unforeseen project delays
    D)
High overhead
    E)
Incentive contracts
    

 
2    
Intense global competition and rapid technological advances create pressure on developing projects rapidly. This is an example of reducing project duration caused by:
    A)
Imposed project deadlines
    B)
Time to market
    C)
Unforeseen project delays
    D)
High overhead
    E)
Incentive contracts
    

 
3    
In a Project Cost-Duration Graph, total project costs are a sum of
    A)
Labor, material and equipment costs
    B)
Direct costs plus interest
    C)
Direct labor costs and the project manager’s salary
    D)
Direct costs and the project manager’s salary
    E)
Direct and indirect costs
    

 
4    
Which of the following is NOT considered a project indirect cost?
    A)
Supervision
    B)
Consultants
    C)
Equipment
    D)
Interest
    E)
The project manager’s salary
    

 
5    
Before crashing, direct costs for an activity represent normal costs, which typically mean low cost, efficient methods for completing the activity in a(n) ________ amount of time.
    A)
Normal
    B)
Budgeted
    C)
Optimized
    D)
Expected
    E)
Targeted
    

 
6    
As a project is crashed and project duration is reduced, direct costs typically
    A)
Increase
    B)
Become unstable
    C)
Decrease
    D)
Become unreliable
    E)
Stay the same
    

 
7    
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.
    A)
Normal
    B)
Reserve
    C)
Crash
    D)
Accelerated
    E)
Expedited
    

 
8    
Cost slope can be determined by dividing the
    A)
Run by the rise
    B)
Rise by the run
    C)
Crash cost by the normal cost
    D)
Normal cost by the crash cost
    E)
Indirect cost by direct cost
    

 
9    
In selecting the best activity to crash you would first select the activity with the
    A)
Earliest start time
    B)
Most steep slope
    C)
Least steep slope
    D)
Longest duration
    E)
Largest crash time
    

 
10    
Reducing project duration
    A)
Involves crashing all activities to their crash point
    B)
Can only be done when resources are not constrained
    C)
Is always more expensive
    D)
Tends to increase network sensitivity
    E)
Should be considered for all projects
    

 
11    
The relationship between the normal point and the crash point is assumed to be:
    A)
Linear
    B)
Curvilinear
    C)
Variable
    D)
Conversely related
    E)
Exponentially related
    

 
12    
When a project manager must reduce project duration but resources are constrained, creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of
    A)
Fast-Tracking
    B)
Using critical-chain project management
    C)
Reducing project scope
    D)
Compromising quality
    E)
Doing it twice- first fast and then ly
    

 
13    
One way of reducing project costs is identifying tasks that _________ can do themselves.
    A)
Vendors
    B)
Suppliers
    C)
Customers
    D)
Company employees
    E)
Project teams
    

 
14    
Which of the following projects would be least beneficial if additional resources were added?
    A)
Splitting and stacking a cord of wood
    B)
Developing new software
    C)
Harvesting a crop by hand
    D)
Building a cabin
    E)
Moving to a new house
    

 
15    
It is going to cost $80,000 a day to simply house and feed a construction crew in the farthest reaches of Northern Alaska. This is an example of reducing project duration due to
    A)
Imposed project deadlines
    B)
Time to market
    C)
Unforeseen project delays
    D)
High overhead
    E)
Incentive contracts

 

Order a unique copy of this paper
(550 words)

Approximate price: $22

Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees


We value our customers, and so ensure that our papers are 100 percent original. Our Team of professionals does not miss the mark; they ensure that step by step each paper is written uniquely. We never duplicate or work as we compare papers rest assured. We deliver our work a day before time to ensure that you don’t miss your deadlines. It is not only doing the work but delivering it at the right time. We capture the consequences of late remittances. .

Money-back guarantee

We value customer satisfaction here at popularessaywriters.com and make sure that you get the best value for your Money. It happens that sometimes you can pay twice for your order or may want to cancel it, or you feel that it doesn’t meet your requirements; our money back guarantee will give you the opportunity to get back your money. We will also refund 100% of money paid double. In case your paper does not satisfy your requirements , we request that you notify us via writing within 2 days otherwise on the third day we will assume that you have been satisfied. Do all your correspondences through our email address popularessaywriters@gmail.com.

Read more

Zero-plagiarism guarantee

At popularessaywriters.com, our professional writers know the consequence plagiarism does for our clients. We have updated software’s such as article checker and copyscape to check for originality of the custom papers before submission of the final paper to the you. Our guarantee to the customer is that we will write 100% original papers for them that are quality, timely and of low cost. We have experienced professional and competent PhD writers who will write quality custom papers for you..

Read more

Free-revision policy

. At popularessaywriters.com, we are proud to provide top-quality Essay writing service to our esteemed customers. We are ready to take up that challenging academic assignment that is giving you sleepless nights and simplify it for you according to your desired requirements. We are willing to revise your paper if it does not meet your requirements. At popularessaywriters.com, we do not compromise with quality; thus, we offer unlimited free revisions until the customer is satisfied with their custom paper. Our unlimited free revision services are provided under the following terms:.. .

Read more

Privacy policy

Popularessawriters.com knows that client’s information is an essential tool for our company. It means that whatever the client requests from our service is kept strictly confidential. It means that whoever writes for this company understands the terms and conditions hence you should not be worried because you will never see your work somewhere else...

Read more

Fair-cooperation guarantee

Rest assured that we will always be attentive to your needs and requirements. We belief in the phrase treat your neighbour as you would want them to treat you. We leave nothing to chance and always look forward to a good interaction with each other.. .

Read more

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency